Building Development

Did you know, we're currently in the

process of refubishing our building?

 

January - December 2010

1. Replacement of heating system to Lounge Area, Kitchen, Disabled Toilet and Office - installation of Central heating system, removal of all individual gas heaters. = COMPLETE

2. Complete electrical upgrade to Lounge area. = COMPLETE

3. Installation of computer network for use in our Youth Projects. = COMPLETE

4. Installation of new electric projection screen and projector = HALF COMPLETE - need new projector

5. Removal of all fitted furniture and installation of new drinks and serving area = COMPLETE

6. Upgrade to Fire Alarm and Emergency Lighting System = HALF COMPLETE - Fire Alarm to complete

7. Installation of new sound system to lounge area. = COMPLETE

8. Completion of disabled toilet and compliance with all DDI regulations completed.= ONGOING

9. Complete redecoration to lounge and entrance areas. = COMPLETE

 

Jan - December 2011

1. Installation of Suspended ceiling to main hall

2. Removal of all gas heater and installation of new Central Heating System

3. Upgrade to sound and AV suite area

4. Complete insulation of main hall (secondary glazing, insulation to main pillar supports)

5. Complete redecoration of main hall and auxillary areas

6. Installation of sound boards to rear wall

7. Fire Alarm and Emergency Lighting Upgrade

8. Upgrade and installation of new kitchen and associated equipment = COMPLETE

 

How much, we hear you ask?

 

Throughout 2010-2011 we need to raise approx

£20,000.00 to complete our

refurbishment and upgrade works

 

CAN YOU HELP?

All gifts can be made via a secure link on our hompage