Building Development
Did you know, we're currently in the
process of refubishing our building?
January - December 2010
1. Replacement of heating system to Lounge Area, Kitchen, Disabled Toilet and Office - installation of Central heating system, removal of all individual gas heaters. = COMPLETE
2. Complete electrical upgrade to Lounge area. = COMPLETE
3. Installation of computer network for use in our Youth Projects. = COMPLETE
4. Installation of new electric projection screen and projector = HALF COMPLETE - need new projector
5. Removal of all fitted furniture and installation of new drinks and serving area = COMPLETE
6. Upgrade to Fire Alarm and Emergency Lighting System = HALF COMPLETE - Fire Alarm to complete
7. Installation of new sound system to lounge area. = COMPLETE
8. Completion of disabled toilet and compliance with all DDI regulations completed.= ONGOING
9. Complete redecoration to lounge and entrance areas. = COMPLETE
Jan - December 2011
1. Installation of Suspended ceiling to main hall
2. Removal of all gas heater and installation of new Central Heating System
3. Upgrade to sound and AV suite area
4. Complete insulation of main hall (secondary glazing, insulation to main pillar supports)
5. Complete redecoration of main hall and auxillary areas
6. Installation of sound boards to rear wall
7. Fire Alarm and Emergency Lighting Upgrade
8. Upgrade and installation of new kitchen and associated equipment = COMPLETE
How much, we hear you ask?
Throughout 2010-2011 we need to raise approx
£20,000.00 to complete our
refurbishment and upgrade works
CAN YOU HELP?
All gifts can be made via a secure link on our hompage
or email Chris for more details by clicking Here
Smethwick Elim Pentecostal Church is a branch of the International Elim Pentecostal Church. A Registered Charity number 251549 
